Pumping Prescriptions
by Lev Nelik
Pumping Machinery LLC

First in a Series

Editor’s Note: Barry T. Brown of Spurlock Station, Unit 2, East Kentucky Power Cooperative contributed to this column.

Three double-suction horizontal split-case pumps installed around 2009 have had mechanical seal issues since installation. Of the four power generation units at East Kentucky Power, Unit 2 was the only one demonstrating these problems.

The unusual installation configuration (vertical position) made plant personnel wonder if such an orientation might be contributing to the problems.

If so, significant modifications would be required to convert the system to a more typical (horizontal) position.

The pumps (2A, 2B and 2C) handle clean cooling water at 100 F, with suction pressure at approximately 20 pounds per square inch gauge (psig) and discharge at 70 psig. The water is then pumped into an 18-inch discharge header. The pumps are driven by 200-horsepower (hp) electric motors at 1,778 revolutions per minute (rpm) with no variable frequency drive (VFD) control.

Plant personnel planned to investigate the following items to determine possible causes of the seal problems:

  • Pump operation, including actual operating flow range versus best efficiency point (BEP) according to the original equipment manufacturer (OEM) curve
  • Possible improper installation (misalignments, piping loads, etc.)
  • Seal flush/vent issues and similar design-related aspects
Suction and discharge pipingImages 1. Suction and discharge piping (Images courtesy of the author)
Suction and discharge pipingImages 2. Suction and discharge piping (Images courtesy of the author)

Pump Operation

A pump reliability and efficiency measurement system (PREMS-2A) data acquisition system was installed to troubleshoot this case and to track parameters related to both pump reliability (vibrations, temperatures) and performance (head-capacity, power and efficiency). The system acquired data every 2 seconds and displayed it on the computer screen every 10 seconds. Both remote (cell tower gateway) and local access were verified to successfully transmit data.

The system was then set to a local mode (PC connected directly to the PREMS-2A chassis) and collected data continually for 16 hours for Pump 2A, 36 hours for Pump 2B and 106 hours for Pump 2C. Collecting this data allowed plant personnel to determine two objectives:

  • actual operating flow range
  • any possible transient events (vibrations, including spectral fast Fourier transform [FFT] data logging)

The following data was routed to the PREMS-2A measurement system: suction and discharge pressures, two temperatures at the upper bearing housing, two vibration inputs (with-flow and perpendicular-to-flow directions off the bearing housings), motor amps and flow (using an ultrasonic flow meter).

Using these data points, the plant’s team could then calculate motor power and overall efficiency.

Location of the ultrasonic flow metersImages 3. Location of the ultrasonic flow meters
Location of the ultrasonic flow metersImages 4. Location of the ultrasonic flow meters

Pressures

Transducers were then connected to quarter-inch tabs teed-off the existing pressure gauge connections (see Images 1 and 2).

Flow

The team tried three ultrasonic flow meters:

  • Dynasonic D902 (Doppler type)
  • Dynasonic DXNP-RW (combination type, with both Doppler and transient time probes)
  • GE 878 (transient time)

Transient time ultrasonic technology is best for clean liquids and requires a straight distance of roughly 10 to 15 pipe diameters, while the Doppler type is better for dirty liquids or at positions where significant turbulence is present (such as near elbows).

After several hours of trial-and-error positioning at various places along the steel pipe header (18-inch outer diameter [OD] with 3/8-inch wall thickness), the team’s attempts to obtain a signal from the Dynasonic meters were not successful.

The GE 878 meter, however, was able to start producing a steady repeatable signal within 20 minutes of installation (see Images 3 and 4).

Two pickup ports were hot-tapped at the header for the pitot type traverse flow meter to compare the ultrasonic flow data.

Current transformer coilImage 5. Current transformer coil (CT) was installed over one of the motor phases.

Amps & Power

A current transformer (CT) coil was installed at the motor leads, approximately 100 feet away from the pumps/motors (see Image 5).

The PREMS-2A system calculates the power via one of the two methods (rated amps/power versus actual reading) or a direct method by multiplying the amps by volts, power factor, motor efficiency and a three-phase constant.

It calculates efficiency using the PREMS-2A internal program (the direct amps method is typically simpler and was selected in this case), which continually displayed the data on the computer screen in the form of actual performance (H-Q, power and efficiency curves versus OEM expected results).

Because of earlier issues with the Dynasonic instrument flow measurements, the team was unable to acquire the efficiency curve in time. By the time the GE 878 was applied successfully, the PREMS-2A was already removed, and the flow data had to be back-fed into it after the test.

Vibrations & Temperatures

The vibration and temperature probes have magnetic bases, and their installation was simple and quick.

Part 2 of this series will discuss data trends and analysis from this case study. Read it here.

References

  1. L. Nelik, Pumps & Systems, July, August, September, October 2015, “Efficiency Monitoring Saves Plants Millions” – in four parts
  2. PREMS-2A Pumps On-Line Efficiency and Reliability Monitoring: http://www.pumpingmachinery.com/pump_school/PVA/pva.htm (model #11)
  3. L. Nelik, “Analysis of the Thermal Behavior in the Sealing Cavity of an Overhung API Process Pump,” Proceedings of 8th International Pump Symposium, Texas A&M, March 3-5, 1991
See other Pumping Prescriptions articles here.